Monday, February 17, 2014

February 15, 2014

Our drywall crews are moving their way through the apartments and as we pass inspections we have the painters following right behind.  We should be close to finishing all the drywall in the next few weeks.  Our painters have also been prepping the existing door frames as we wait to hear on a color choice from the architect.  The wood doors were delivered this past week and the metal doors are scheduled for delivery this week.

 Unit 115 existing door frame removed

 Unit 215 HP-1 wall sleeve caulked

 Unit 219 switched outlet for garbage disposal

 Unit 413 Dens-Shield installed in shower

Unit 414 sheetrock and taping

 Unit 414 kitchen painted with primer

Monday, February 3, 2014

January 31, 2014

We worked with the City to get our rough-in issues resolved and passed our plumbing and HVAC inspections.  We have crews working on insulation, sheetrock, and fire caulking and will have inspections for those towards the beginning of the month.  We should be ready to paint in a couple weeks.  The fire alarm control panel was recently installed along with a new handicap ramp out by the street.

New 16" splice cabinet in Unit 113 - Approved by LA City

Unit 213 Insulation installed

Unit 316 new waste and vent stack

Unit 413 Sheetrock

HP-1 wall sleeves in 13, 14, 15 & 16 apartment stacks

Level 1 new Fire Alarm pull station

New FACP in Entrance Foyer

New flue piping for boilers

Equipment platform for condensing units with roofing membrane installed

Finished Handicap Ramp

Tuesday, January 14, 2014

January 15, 2014

All Apartments in Phase 1 (113-119, 213-219, 313-319, 413-419) are finished framing, rough in electrical, rough in plumbing (waste and vent as well as water lines), door frames installed and ready for sheetrock.  However, we have run in to a few unforeseen conditions and requests from the City regarding the design that need to be addressed before we can move to the next stage of the project.  We are trying hard to resolve those concerns so we can start sheetrock in the next week.  The stair lift is scheduled to be installed in 5 weeks, H/C ramps and truncated domes next week.  The painter is going to start preparing all of the existing door frames in the next couple of days.  The condensing unit platforms on the roof started to be framed yesterday.  We will be complete with rough in fire alarm by 1/17/14.

 Phase 1 Courtyard view

 Storage containers for Owner Furnished furniture

 Unit 115 framing, rough in electrical and plumbing finished

 Unit 117 junction box with wire for FA outside

 Unit 218 rough in complete pending revisions by the City

 Unit 319 bathroom

 Unit 319 lintel and door frame installed

 Unit 319 water supply complete

 Unit 414 bi-fold door framing installed

 Unit 414 existing plumbing waste stack has been removed

Unit 419 pocket door frame installed

Friday, January 3, 2014

December 2013

Currently, we are in the inspection stages for all the rough in plumbing, electrical, framing, fire alarm and HVAC.  Upcoming schedule for the next 3 weeks is:
1/10/14- 1/14/14: Finish all framing, rough in plumbing, electrical, HVAC and fire alarm.  
City inspections scheduled throughout this week.
1/15/14- 1/24/14: Insulate walls and sheetrock apartments.  Sheetrock will be finished 
Feb 12th.  We will begin painting behind the sheetrock on 1/27/14 and tile and cabinets 
should be installed the first of February.

The pace of this project will really pick up over the next couple of months as we now have all of the required permits, Owner Furnished items and problems resolved.


 New windows and doors at Units 213-216, 313-316, 413-416

 Windows and patio doors complete in Phase 1

 Windows and patio doors complete in Phase 1

 Windows complete in Phase 1

Unit 316 ready for cover up inspection

Water supply in Unit 117

Lintel installed in Unit 119

 Electrical rough in Unit 118

 Exhaust fan venting Unit 218

 Framing, rough plumbing, electrical and shaft wall sheetrock Unit 115

 Openings for HVAC wall units reframed and outlets relocated Unit 417

Water supply and bathtub Unit 319

New pitch pockets at exhaust fan and refrigerant line penetrations

Monday, December 9, 2013

November 30, 2013


Apartment 115 finished slab

Apartment 119 finished slab

Apartment 213 existing plumbing hole patched

Unit 413 shaft wall sheet rock first layer

Unit 418 bathroom window with heavy duty screen

Bathtub installed in Unit 219
Courtyard view of fourth floor windows

Framing in Apartment 114

Framing in Apartment 115

Kohler bathtub ready for install

New windows in Units 417-419

Finishing concrete plumbing patch in Unit 113

Pumping concrete to first floor units Phase 1