Friday, January 3, 2014

December 2013

Currently, we are in the inspection stages for all the rough in plumbing, electrical, framing, fire alarm and HVAC.  Upcoming schedule for the next 3 weeks is:
1/10/14- 1/14/14: Finish all framing, rough in plumbing, electrical, HVAC and fire alarm.  
City inspections scheduled throughout this week.
1/15/14- 1/24/14: Insulate walls and sheetrock apartments.  Sheetrock will be finished 
Feb 12th.  We will begin painting behind the sheetrock on 1/27/14 and tile and cabinets 
should be installed the first of February.

The pace of this project will really pick up over the next couple of months as we now have all of the required permits, Owner Furnished items and problems resolved.


 New windows and doors at Units 213-216, 313-316, 413-416

 Windows and patio doors complete in Phase 1

 Windows and patio doors complete in Phase 1

 Windows complete in Phase 1

Unit 316 ready for cover up inspection

Water supply in Unit 117

Lintel installed in Unit 119

 Electrical rough in Unit 118

 Exhaust fan venting Unit 218

 Framing, rough plumbing, electrical and shaft wall sheetrock Unit 115

 Openings for HVAC wall units reframed and outlets relocated Unit 417

Water supply and bathtub Unit 319

New pitch pockets at exhaust fan and refrigerant line penetrations