Tuesday, January 14, 2014

January 15, 2014

All Apartments in Phase 1 (113-119, 213-219, 313-319, 413-419) are finished framing, rough in electrical, rough in plumbing (waste and vent as well as water lines), door frames installed and ready for sheetrock.  However, we have run in to a few unforeseen conditions and requests from the City regarding the design that need to be addressed before we can move to the next stage of the project.  We are trying hard to resolve those concerns so we can start sheetrock in the next week.  The stair lift is scheduled to be installed in 5 weeks, H/C ramps and truncated domes next week.  The painter is going to start preparing all of the existing door frames in the next couple of days.  The condensing unit platforms on the roof started to be framed yesterday.  We will be complete with rough in fire alarm by 1/17/14.

 Phase 1 Courtyard view

 Storage containers for Owner Furnished furniture

 Unit 115 framing, rough in electrical and plumbing finished

 Unit 117 junction box with wire for FA outside

 Unit 218 rough in complete pending revisions by the City

 Unit 319 bathroom

 Unit 319 lintel and door frame installed

 Unit 319 water supply complete

 Unit 414 bi-fold door framing installed

 Unit 414 existing plumbing waste stack has been removed

Unit 419 pocket door frame installed