All Apartments in Phase 1 (113-119, 213-219, 313-319, 413-419) are finished framing, rough in electrical, rough in plumbing (waste and vent as well as water lines), door frames installed and ready for sheetrock. However, we have run in to a few unforeseen
conditions and requests from the City regarding the design that need to be addressed before we can
move to the next stage of the project. We are trying hard to resolve those concerns so we can start sheetrock in the
next week. The stair lift is scheduled to be installed in 5 weeks, H/C
ramps and truncated domes next week. The painter is going to start preparing
all of the existing door frames in the next couple of days. The
condensing unit platforms on the roof started to be framed yesterday. We will
be complete with rough in fire alarm by 1/17/14.
Phase 1 Courtyard view
Storage containers for Owner Furnished furniture
Unit 115 framing, rough in electrical and plumbing finished
Unit 117 junction box with wire for FA outside
Unit 218 rough in complete pending revisions by the City
Unit 319 bathroom
Unit 319 lintel and door frame installed
Unit 319 water supply complete
Unit 414 bi-fold door framing installed
Unit 414 existing plumbing waste stack has been removed
Unit 419 pocket door frame installed