January 31, 2014

We worked with the City to get our rough-in issues resolved and passed our plumbing and HVAC inspections.  We have crews working on insulation, sheetrock, and fire caulking and will have inspections for those towards the beginning of the month.  We should be ready to paint in a couple weeks.  The fire alarm control panel was recently installed along with a new handicap ramp out by the street.

New 16" splice cabinet in Unit 113 - Approved by LA City

Unit 213 Insulation installed

Unit 316 new waste and vent stack

Unit 413 Sheetrock

HP-1 wall sleeves in 13, 14, 15 & 16 apartment stacks

Level 1 new Fire Alarm pull station

New FACP in Entrance Foyer

New flue piping for boilers

Equipment platform for condensing units with roofing membrane installed

Finished Handicap Ramp