We are in the process of finishing Phase 1 and over the next couple of weeks will be complete with all but
minor items, a couple of Owner Furnished items we are waiting on, or
punchlist items.
Cabinets are complete except minor
punchlist items. Tile is about 2/3 complete and on
the 3rd & 4th floor 100% complete with the exceptions of the 1 bedrooms and
some punchlist items. All apartments have been painted
with the exception of the 1 bedroom units (4 apartments). We are
currently re-painting and touching up the paint in all of the apartments and will wrap that up in the next couple weeks. We are in the process of installing
plumbing fixtures, faucets, toilets, shower heads etc, and will be complete in
the next week and a half. We are also currenlty installing all of the wood
doors, bi-fold doors and hardware in the apartments. The chair lift will be installed on
Thursday and entry locksets with the card readers
will be onsite mid April.
Cleaning of the apartments will
begin next Monday and Steve Garner will begin doing a final punchlist
tomorrow for all of the trades, starting on the 4th floor.
Unit 116 bathroom wall tile
Unit 217 floor tile
Unit 314 floor grouted
Unit 413 bathroom and bifold doors installed
Unit 414 kitchen faucet, sink, and backsplash
Unit 414 new bathroom faucet installed
Unit 414 shower fixtures
Unit 415 toilet installed