Monday, February 17, 2014

February 15, 2014

Our drywall crews are moving their way through the apartments and as we pass inspections we have the painters following right behind.  We should be close to finishing all the drywall in the next few weeks.  Our painters have also been prepping the existing door frames as we wait to hear on a color choice from the architect.  The wood doors were delivered this past week and the metal doors are scheduled for delivery this week.

 Unit 115 existing door frame removed

 Unit 215 HP-1 wall sleeve caulked

 Unit 219 switched outlet for garbage disposal

 Unit 413 Dens-Shield installed in shower

Unit 414 sheetrock and taping

 Unit 414 kitchen painted with primer

Monday, February 3, 2014

January 31, 2014

We worked with the City to get our rough-in issues resolved and passed our plumbing and HVAC inspections.  We have crews working on insulation, sheetrock, and fire caulking and will have inspections for those towards the beginning of the month.  We should be ready to paint in a couple weeks.  The fire alarm control panel was recently installed along with a new handicap ramp out by the street.

New 16" splice cabinet in Unit 113 - Approved by LA City

Unit 213 Insulation installed

Unit 316 new waste and vent stack

Unit 413 Sheetrock

HP-1 wall sleeves in 13, 14, 15 & 16 apartment stacks

Level 1 new Fire Alarm pull station

New FACP in Entrance Foyer

New flue piping for boilers

Equipment platform for condensing units with roofing membrane installed

Finished Handicap Ramp