We worked with the City to get our rough-in issues resolved and passed our plumbing and HVAC inspections. We have crews working on insulation, sheetrock, and fire caulking and will have inspections for those towards the beginning of the month. We should be ready to paint in a couple weeks. The fire alarm control panel was recently installed along with a new handicap ramp out by the street.
New 16" splice cabinet in Unit 113 - Approved by LA City
Unit 213 Insulation installed
Unit 316 new waste and vent stack
Unit 413 Sheetrock
HP-1 wall sleeves in 13, 14, 15 & 16 apartment stacks
Level 1 new Fire Alarm pull station
New FACP in Entrance Foyer
New flue piping for boilers
Equipment platform for condensing units with roofing membrane installed
Finished Handicap Ramp