Currently, we are in the
inspection stages for all the rough in plumbing, electrical, framing, fire
alarm and HVAC. Upcoming schedule for the next 3 weeks is:
1/10/14- 1/14/14: Finish all
framing, rough in plumbing, electrical, HVAC and fire alarm.
City
inspections scheduled throughout this week.
1/15/14- 1/24/14: Insulate walls and
sheetrock apartments. Sheetrock will be finished
Feb 12th. We will begin painting behind the
sheetrock on 1/27/14 and tile and cabinets
should be installed the first
of February.
The pace of this project will really
pick up over the next couple of months as we now have all of the required
permits, Owner Furnished items and problems resolved.
New windows and doors at Units 213-216, 313-316, 413-416
Windows and patio doors complete in Phase 1
Windows and patio doors complete in Phase 1
Windows complete in Phase 1
Unit 316 ready for cover up inspection
Water supply in Unit 117
Lintel installed in Unit 119
Electrical rough in Unit 118
Exhaust fan venting Unit 218
Framing, rough plumbing, electrical and shaft wall sheetrock Unit 115
Openings for HVAC wall units reframed and outlets relocated Unit 417
Water supply and bathtub Unit 319
New pitch pockets at exhaust fan and refrigerant line penetrations