Friday, May 16, 2014

May 15, 2014

Patrons are moving into the completed Phase 1 and the Owner is currently removing furnishings from Phase 2.

 Owner donating appliances from Phase 2 to Mission homes

 Owner donating furniture from Phase 2

 Stacking Owner furnished tile in storage container

Taking inventory of Owner furnished tile

Thursday, May 1, 2014

May 1, 2014

The construction finishes are in and we have been working on punch list items and getting final inspections from the City.  The Owner has started bringing in and arranging the furnishings.  We've noted some items that will need coordination on future phases to help better tie things together.

Unit 115 accessible shower

Unit 119 backsplash being installed

Unit 313 with furniture

Unit 319 bedroom carpet and base installed

Unit 413 blinds installed

Unit 413 living room blinds

Unit 413 Owner arranged furniture

Unit 413 Owner arranged furniture

4th floor corridor aggregate paint applied

Painting outside of the concrete on the roof ledge and corridor walkways

April 15, 2014

The chair lift went in and we are wrapping up a lot of finish items and working towards getting our final inspections taken care of in homes of wrapping up Phase 1 by the end of the month.

4th floor railings sanded and painted

Unit 116 accessible unit wall mounted sink and toilet

Unit 119 floor tile installed - needs grout

Unit 319 bathtub tile

Chair Lift


Roof top units HP-2 set - installing power