Tuesday, April 1, 2014

March 31, 2014

We are in the process of finishing Phase 1 and over the next couple of weeks will be complete with all but minor items, a couple of Owner Furnished items we are waiting on, or punchlist items.
  
Cabinets are complete except minor punchlist items.  Tile is about 2/3 complete and on the 3rd & 4th floor 100% complete with the exceptions of the 1 bedrooms and some punchlist items.  All apartments have been painted with the exception of the 1 bedroom units (4 apartments).  We are currently re-painting and touching up the paint in all of the apartments and will wrap that up in the next couple weeks.  We are in the process of installing plumbing fixtures, faucets, toilets, shower heads etc, and will be complete in the next week and a half.  We are also currenlty installing all of the wood doors, bi-fold doors and hardware in the apartments.  The chair lift will be installed on Thursday and entry locksets with the card readers will be onsite mid April.

Cleaning of the apartments will begin next Monday and Steve Garner will begin doing a final punchlist tomorrow for all of the trades, starting on the 4th floor.  

 Unit 116 bathroom wall tile

 Unit 217 floor tile

 Unit 314 floor grouted

 Unit 413 bathroom and bifold doors installed

 Unit 414 kitchen faucet, sink, and backsplash

 Unit 414 new bathroom faucet installed

 Unit 414 shower fixtures

Unit 415 toilet installed